Auxiliary generator optimisation for a tanker fleet, phase 1

Six months of data from the four auxiliary engines on three sister vessels assessed and mapped, establishing the base for generator optimisation and fleet benchmarking.

Challenge

A shipping operator wanted to reduce energy consumption at sea by using its generators better. The data from the four auxiliary engines and generators on three sister vessels had never been assessed for that purpose.

Solution

Arundo took in about six months of data per vessel across fuel, engine, turbocharger, lubrication, cooling and generator tags, validated continuity and sampling against the class society's own resampling, mapped the sensors across engines, derived on/off states from RPM and temperature, and separated trips from transient loads.

Impact

Data quality confirmed good enough for operational optimisation, with the sampling-rate and mapping issues named; the recommended next step was generator optimisation from single generator to fleet benchmarking.

Where is your plant on the scale?

Thirty minutes with our team, and you'll know your plant's level, the constraint holding it there, and what Level +1 is worth to you.

Find your plant's level Book a level assessment